East Shuswap Road

EAST SHUSWAP ROAD

Road Realignment

Project Name

Partner

Project Manager

Project Manager Contact

EAST SHUSWAP ROAD: Road Realignment

Argo Roads for the Ministry of Transportation & Infrastructure

Brook Webster

bwebster@arrow.ca
(250) 571-6085

Project Location

Project Award Date

Project Completion Date

Kamloops, BC

October 1, 2020

November 9, 2020

Project Details

The South Thompson River eroded a 300-meter section of East Shuswap Road, making the road unstable. Argo reduced the section of road to single lane traffic until a solution could be found to make it safe for the traveling public. Arrowhead was contracted to move the alignment of the road away from the unstable embankment.

Project Services and Scope

Project services Arrowhead provided include:

  • clearing and grubbing of trees and light brush
  • stripping of organic materials
  • removal of existing asphalt
  • earthworks for the new road alignment
  • placement of granular road structure
  • placement of asphalt
  • installation of Concrete Roadside Barrier (CRB)
  • line painting